RFI Log: Architect’s Defense Against Claims
In the high-stakes world of architecture, construction and contract administration, memory is a poor witness.
When a construction project hits a snag, a conflict between the structural steel and the HVAC ducting, or a finish specification that’s no longer available, the inevitable “who knew what and when” argument begins between parties.
In the era of 30-day adjudications, “email” is not a legal defense. If you cannot prove your timeline with neutral, third-party data, the Architect’s professional liability and the project’s profit margin are both at risk.

The RFI: The Heartbeat of Design Intent
The Request for Information (RFI) is the formal bridge between the Architect’s vision and the Contractor’s execution. In professional contract administration, it follows a strict, legally significant lifecycle:
- Identification: A contractor discovers a discrepancy in the construction documents (e.g., a window flashing detail that doesn’t meet site conditions).
- Formal Submission: A request is issued to the Architect, ideally referencing specific drawing sheets and requesting a clarification or Supplemental Instruction (SI).
- The Response: The Architect provides a formal answer. This response often serves as a “mini-contract,” clarifying exactly how a detail will be built and whether it constitutes a change in scope.
The Problem: The Chaos of the Inbox
In many projects, this “heartbeat” is erratic. Emails are scattered, easily buried, and most importantly local to the sender or receiver. Imagine this scenario:
A Contractor discovers a major structural clash on Tuesday. They claim they sent a critical RFI via email at 4:00 PM that afternoon, assuming the clock had started and the Architect was now responsible for the delay. You, the Architect, claim you didn’t receive it until Friday. In those three days, the contractor kept their crew on standby, racking up $15,000 in “delay damages” they now want you to pay.

Who wins?
In a traditional email setup:
- The Contractor shows a “Sent” receipt from their local computer.
- The Architect shows a “Received” timestamp from their server three days later.
The adjudicator, who typically decides cases on documents alone without oral hearings, is left with a “He Said, She Said” stalemate. Without a neutral record, the party with the better-organized paper trail usually walks away with the cheque.
The RForm Angle: The Power of the “Server-Side” Timestamp
RForm contract administration software changes the game by creating a digital Single Source of Truth. It doesn’t matter when an email was “sent” or when an inbox was “opened.” It only matters when the record was Created.
| Traditional Email | The RForm Neutral Log |
| Local Timestamps: Can be affected by time zones, server lag, or “outbox” delays. | Server-Side Accuracy: RForm stamps the exact second an RFI is Created. This is a neutral, third-party record that cannot be manipulated by either party. |
| “I Didn’t Get It”: Claims of spam filters or “lost” emails are common excuses used to shift blame. | Instant Availability: The moment an RFI is created, it is legally “available” to the Architect and consultants. The “I didn’t see it” defense fails when the log shows it was there. |
| Fragmented Replies: Design clarifications get lost in long, messy threads with multiple consultants. | Hard-Linked Responses: Every Reply Date is permanently tied to the original RFI, creating a closed-loop timeline that shows exactly how long the “ball” was in the Architect’s court. |
Why “Creation Date” is the Legal Baseline
By focusing on the Creation and Reply dates, RForm eliminates the ambiguity of human behavior. In an adjudication:
- The Log is Immutable: Unlike an email chain that can be selectively printed or “lost,” the RForm log is a permanent record of the project. It cannot be altered after the fact to hide a slow response.
- Forensic Precision: You aren’t presenting “your version” of events. You are presenting the project’s actual history as recorded by a neutral system.
- Accountability: If the log shows the RFI was Created on Tuesday, the Architect is accountable for the response time. If the log shows it wasn’t actually created until Friday regardless of what the Contractor’s “Sent” folder says the claim for Tuesday-to-Thursday delay damages is instantly dismissed.
The Bottom Line
Your RFI log is either a shield or a target. For an Architect, a manual spreadsheet and an outlook search are not enough to protect your firm from delay claims.
By using a platform like RForm that tracks the exact moment of creation and response, you ensure that when the adjudicator asks for the facts, your log does the talking for you.

Ready to transform your contract administration?

